Digital Infrastructure Modernization for Engineering Firm
Client: WING FAT BUILDING CONSTRUCTION LIMITED
Successfully migrated 20 years of legacy data to a resilient hybrid cloud infrastructure, enhancing data availability and operational efficiency.

The Challenge
Wing Fat, a long-established engineering and construction company, faced significant operational bottlenecks due to their aging on-premises server infrastructure. Accessing decades of project data was slow and unreliable, hindering collaboration and decision-making. They needed a modern, scalable, and highly available solution without disrupting ongoing operations.
Our Approach
We executed a phased digital transformation strategy focused on infrastructure modernization and seamless data migration:
- Designed a hybrid cloud infrastructure leveraging both private and public cloud resources for optimal cost, performance, and security.
- Developed a meticulous data migration plan to seamlessly transfer over 20 years of critical project data from legacy systems.
- Implemented robust data synchronization and validation processes to ensure data integrity throughout the migration.
- Deployed high-availability and disaster recovery mechanisms to guarantee business continuity and data resilience.
Results & Impact
99.99%
Achieved data availability uptime
5x
Improvement in data access speed
100%
Cost saving
The modernized hybrid infrastructure provided Wing Fat with significantly improved performance, scalability, and data resilience. The seamless migration minimized business disruption. Engineers and project managers now benefit from faster, reliable access to critical data, enhancing collaboration and accelerating project timelines. The new infrastructure provides a solid foundation for future digital initiatives.
“Migrating two decades of data felt daunting, but ACMR Tech managed it flawlessly. Our systems are faster, more reliable, and the team finally has the data access they need. The transition was smoother than we could have hoped for.”
— IT Director, WING FAT BUILDING CONSTRUCTION LIMITED
Technologies Used
Project Timeline
Duration: 9 months
- Infrastructure Assessment & Design: 2 months
- Pilot Migration & Testing: 1.5 months
- Phased Data Migration: 4 months
- System Cutover & Validation: 1 month
- Post-Migration Support: 0.5 months
Modernize Your Infrastructure?
Let's discuss how our digital transformation and cloud solutions can enhance your business's resilience and efficiency.
Get in TouchExplore More Case Studies
Integrated Ticketing & Event Platform for Nightlife
Client: Until Blank
Developed a seamless mobile app, ticketing platform, and e-commerce system, drastically improving event entry and payment processes.